MoSCoW
Must Haves are the bare minimum.
- Must haves should be no more than 60%, and should be at a level where the teams confidence to deliver them is high
- The lower the better
- Could haves should be no larger than 20%

Only go over 60% if:
- Estimates are known to be accurate
- The approach is very well understood
- The team are “performing”
- The environment is understood and low-risk in terms of the potential for external factors to introduce delays
Prioritiseation
Find a quantifiable reason to swap requirements between should have and could have
The prioritisation should be reviewed every Time-box